Shaft Excavator

 
   

Bennett Associates' reputation for mechanical engineering design, coupled with its rapid response and solution finding capability, has once again been put to good use.

Difficulties in sinking shafts under balanced head conditions through hard clay on NORTH WEST WATER LTD's Fylde Coastal Water Improvement scheme prompted AMEC Tunnelling to contact Bennett Associates to design a solution.

Overall requirements were established and a brief feasibility appraisal produced a conceptual design which incorporated new equipment working in combination with AMEC's existing spoil removal shaft grab arrangements.

An order was placed on Bennett Associates to carry out the development, detail design and project management of the manufacture of the complete system.

Following a six week development and detailed design period, manufacturing was carried out within eight working weeks of order placement on the suppliers.

The system is designed for use within a 6mm internal diameter shaft, sinking to a depth of 35m. The hydraulically powered telescopic excavator assembly, incorporating fixed and rotating supporting rings, allows full excavation of the shaft bottom extending out to the shaft cutting edge.

 
   
Page 1Page 2Next Page

 
Shaft Excavator - Tunnelling
Shaft Excavator

Shaft Excavator - Tunnelling
Shaft Excavator - Tunnelling
Shaft Excavator - Tunnelling
     
     
Move mouse over images to enlarge


Printable PDF
Pdf