Atkins Rotherham

Engineering Design Consultants

Atkins - the official engineering design services provider for the London 2012 Olympic and Paralympic Games
RSS feed
20 Years in Worldwide Tunnelling

From Folkestone to Hong Kong - 20 years in Worldwide Tunnelling

   

A tunnelling project that bored 40m under the sea floor, for a distance of 38km, would undoubtedly present an epic challenge. Back in 1988, the Channel Tunnel project was to become the starting point for Bennett Associates' journey into the world of tunnelling. Over the past 20 years, they have developed an extensive experience and wide range of capabilities within the worldwide tunnelling industry.

Working alongside clients, contractors and manufacturers, they have been involved with some of the world’s largest tunnelling projects including the Channel Tunnel, Channel Tunnel Rail Link, Hong Kong Underground, Storebaelt Tunnel in Denmark, the Heathrow Express and most recently, major projects in Asia. Their expertise, innovation and flexibility has enabled them to provide practical, cost effective solutions to a broad spectrum of tunnelling problems.

Channel Tunnel
At 50 km (of which 38km is undersea), the Channel Tunnel is a feat of modern engineering and has been declared by The American Society of Civil Engineers to be one of the Seven Wonders of the Modern World. Bennett Associates designed and produced detailed manufacturing drawings for the 235m long back-up system to the Tunnel Boring Machine (TBM) for the Channel Tunnel, the world’s largest undersea tunnelling project. They were also responsible for carrying out a full stress analysis of the cutter head support, TBM structure and gripper body and pads which was done by Finite Element analysis using ANSYS software solid modelling elements. The analysis was used interactively by the Robbins designers in Seattle USA. Close co-operation was maintained by visits to Seattle and exchange of AutoCAD drawings to ensure that the complex interface between TBM and its back-up system was correctly engineered.

TBM and backup design
Bennett Associates understand the complexities and potential problems that can challenge tunnelling projects. Their knowledge and flexibility can provide cost effective, reliable solutions that will keep the Tunnel Boring Machines on schedule throughout the project. Through their experience and knowledge of Tunnel Boring Machines and backup design, whether drilling through hard rock, clay or a combination of materials, Bennett’s expertise can provide detailed design solutions and complete integration of tunnelling systems for all ground conditions. Their reference list includes the following machine types:

.
Hard Rock
.
Earth Pressure Balance Machine (EPBM)
.
Clay
.
Slurry
.
Universal/Combination
.
Excavator
.
Hand Shields

Materials Handling
Bennett Associates have a worldwide reputation for providing materials handling solutions as part of the backup system. Bulk material handling systems design expertise, principally gained from coal handling, stacking and reclaiming plant allied to the power industry, encompasses production of plant layout and detailed layout/manufacturing drawings. Their experience includes:

.
Muck Conveyors
.
Segment Conveyors, Erectors & Handling
.
Screw Conveyors

Conversions
Tunnel Boring Machines are extremely costly pieces of machinery. Specified exactly to meet the requirements of one project, machines can often become redundant following the completion of a tunnelling project. Bennett’s experience and knowledge has enabled them to offer a conversion service whereby existing redundant plant is checked, surveyed, re-configured and re-designed for use on new tunnel contracts.

Infrastructure
Bennett Associates are well placed to offer effective design solutions to the other infrastructure and support systems necessary to keep tunnelling projects on track. These include Shaft Systems, Pipe Jacking and Handling, Airlocks, Crossovers and Bulkhead Doors together with safety and environmental solutions adapted to specific project requirements.

Their reputation for mechanical engineering design, coupled with their rapid response and solution finding capability, was put to good use by North West Water Ltd’s Fylde Coastal Water Improvement Scheme. AMEC Tunnelling had been experiencing difficulties sinking shafts under balanced head conditions through hard clay. A design was produced which incorporated new equipment working in combination with AMEC's existing spoil removal shaft grab arrangements. Following a six week development and detailed design period, manufacturing was carried out within eight working weeks of order placement on the suppliers.

Bennett’s diverse infrastructure experience also includes designing two 26 metre sliding crossover doors for the Tai Lam tunnel train track in Kowloon, Hong Kong, including the mechanism to close the 45 tonne doors to provide a 4 hour fire barrier. The door system consists of two sliding leaves each approximately 27 metres long and nearly 6 metres high. Each leaf weighs 45 tonnes. They move on two wheels housed in easy-access wheel boxes which run on rails recessed in the concrete floor underneath and fixed in grout. When the door is closed it is lowered to produce a structural gap between door and floor of only 10mm.

Tunnelling within the confines of a built up area can pose many logistical problems. During the work on the passenger interchange tunnel at Green Park Station for the Jubilee Line Extension, work was carried out around the clock and stringent noise emission parameters were placed upon the constructors by Westminster City Council. In order to reduce noise pollution around the excavation of the access shaft, Bennett Associates designed an ‘Acoustic Shroud’ for main contractors Tarmac Construction Ltd.

Consultancy
Bennett Associates can advise on all aspects of tunnelling including machine selection and specification, technical investigations and safety. Their experience of drilling through a variety of materials means that they are able to recommend cost effective, workable solutions. Bennett’s can be on hand to advise their clients throughout the project, from initial concepts and designs, through to site supervision and fault analysis. Consultancy services include:

.
Machine Suitability
.
Safety/Systems
.
Technical Investigations
.
Fault Analysis
.
Project Management
.
Litigation/Expert Witness
.
3rd Party Checking

Established over the last 20 years, Bennett Associates worldwide reputation in the tunnelling industry is testament to their ability to provide innovative, cost effective and reliable solutions for tunnelling projects at every level.

February 2008

For more information on how Atkins Rotherham can assist with your tunnelling project, please telephone 01709-373782

M G Bennett and Associates Ltd is now part of the Atkins - the official engineering design services provider for the London 2012 Olympic and Paralympic Games Group
Atkins - the official engineering design services provider for the London 2012 Olympic and Paralympic Games
 

Tunnelling Projects

Channel Tunnel
Storebaelt Tunnel - Denmark
Submerged Shaft Excavator - Fylde Coast
Acoustic Canopy - Jubilee Line Extension
Segment Erector - Heathrow Express
KCRC Crossover Doors - Kowloon - Hong Kong
Channel Tunnel Rail Link - Backup Systems
 

One of the Channel Tunnel Boring Machines
One of the Channel Tunnel Boring Machines

vDrill for Department of the State of Jersey Flood relief scheme
Drill for Department of the State of Jersey Flood relief scheme
Novel Tunnel Segment Manipulator
Novel Tunnel Segment Manipulator
Crossover doors for the Tai Lam Tunnel train track Kowloon, Hon Kong
Crossover doors for the Tai Lam Tunnel train track - Kowloon, Hon Kong
Noise pollution remedy during Jubilee Line shaft excavation
Noise pollution remedy during Jubilee Line shaft excavation